Project types
Capacity
240 MW(p)
Project status
Secured land
Country
Poland
Voivodeship
zachodniopomorskie
Grid connection conditions
YES
Operator
PSE
Voltage
399.99 kV
Price
20,000 EUR/MW
Grid Connection Project for the Distribution System (DSO) – BESS 240 MW / 240 MW
Connection Voltage: 400 kV
Energy storage capacity: 240 MW (grid injection) / 240 MW (grid withdrawal)
Planned energization date: June 2034
Estimated grid connection fee: PLN 25,565,500.00 net + VAT
The project involves the connection of a distribution system, integrated with energy storage systems with a total installed capacity of 240 MW (charging and discharging), to the transmission grid.
In accordance with the grid connection conditions issued by Polskie Sieci Elektroenergetyczne S.A. (PSE S.A.), the investment is planned for implementation at a 400 kV voltage level, with the connection point at the 400/220/110 kV Dunowo substation (Busbar in the 400 kV switchgear).
The earliest date for ensuring energization has been set for June 2034, assuming the grid connection agreement is concluded in June 2026. This date may change during the negotiation of the grid connection agreement's terms and depending on the Operator's schedule for network investment implementation.
The estimated connection fee, determined based on the connection conditions, amounts to 25,565,500.00 PLN net + VAT, with the possibility of an update during the conclusion of the connection agreement.
Should you notice any Illegal Content on the Platform, or content that violates the law, good practices, or the Terms and Conditions for the provision of services on the greensearch.pl online platform, please contact us directly at: kontakt@greensearch.pl. Please title the message "Report of Illegal Content on the Platform" and include a description of the violation along with a link to the offer containing the relevant content.