Project types
Capacity
240 MW(p)
Storage Capacity
0 MWh
Project status
Secured land
Country
Poland
Voivodeship
pomorskie
Grid connection conditions
YES
Operator
PSE
Voltage
400 kV
Line length
0 km
Minimum rent
0 PLN/ha
Date BP
01/10/2030
Date of COD
01/10/2030
Energy sale
other
Project sale
Other
Price
20,000 EUR/MW
Connection Voltage: 400 kV
Energy Storage Capacity: 240 MW (grid injection) / 240 MW (grid off-take)
Planned Energization Date: October 2030
Estimated Connection Fee: PLN 14,028,000.00 net + VAT
The project concerns connection to the transmission grid of a non-public distribution system comprising a 240 MW / 240 MW energy storage facility. Connection point - Żarnowiec.
Based on the connection conditions issued by the Transmission System Operator (PSE S.A.), the investment has been qualified for implementation at a 400 kV voltage level, with the energization date set for October 2030, assuming the connection agreement is concluded in 2026.
The estimated connection fee, corresponding to the anticipated investment outlays, amounts to PLN 14.03 million net, with the possibility of adjustment during the implementation phase or upon signing the agreement.
Should you notice any Illegal Content on the Platform, or content that violates the law, good practices, or the Terms and Conditions for the provision of services on the greensearch.pl online platform, please contact us directly at: kontakt@greensearch.pl. Please title the message "Report of Illegal Content on the Platform" and include a description of the violation along with a link to the offer containing the relevant content.