Project types
BESS Power
16 MW
Storage Capacity
68.8 MWh
Project status
Environmental decision obtained
Country
Poland
Voivodeship
śląskie
Grid connection conditions
YES
Operator
Tauron
Voltage
15 kV
Line length
1 km
Minimum rent
50,000 PLN/ha
Date BP
31/12/2027
Date of COD
31/12/2028
Energy sale
other
Project sale
Other
For sale: two identical energy storage projects located in Śląskie Voivodeship (TAURON), at the pre-RTB stage.
Charging capacity: 8 MW
Discharging capacity: 8 MW
Connection capacity: 8,000 kW
Storage capacity: 34.4 MWh
Land secured by a lease agreement.
Length of connection to HV substation: approx. 1000 m (route optimization for both installations)
Grid connection agreement signed.
Planned energization: 30.10.2028.
Connection cost as per the Connection Agreement: 2 x 100,000 PLN gross.
Details, documentation, and plot number are available upon contact through greensearch.
Should you notice any Illegal Content on the Platform, or content that violates the law, good practices, or the Terms and Conditions for the provision of services on the greensearch.pl online platform, please contact us directly at: kontakt@greensearch.pl. Please title the message "Report of Illegal Content on the Platform" and include a description of the violation along with a link to the offer containing the relevant content.