Back
greensearch - BESS logo

BESS - 50 MW pre-RTB COD 2029 (Zachodniopomorskie)

greensearch - BESS

Project types

Energy storage

BESS Power

50 MW

Storage Capacity

228 MWh

Project status

Zoning plan amended

Country

Poland

Voivodeship

zachodniopomorskie

County

Kołobrzeski

Grid connection conditions

YES

Operator

Energa

Voltage

110 kV

Line length

2.9 km

Date BP

30/09/2027

Date of COD

31/01/2029

Project description

The project includes a large-scale energy storage system with a capacity of 50 MW and a storage capacity of 228 MWh.


Key project parameters:

• Energy storage power: 50 MW

• Energy storage capacity: 228 MWh

• Storage duration: over 4 hours

• Charging capacity: 50 MW

• Discharging capacity: 50 MW

• Connection voltage: 110 kV

• Grid operator: ENERGA-OPERATOR S.A.

• Estimated connection length: approx. 2.9 km

• Estimated connection cost: 1,250,000 PLN

• Planned connection date: 31.01.2029

• Planned RTB status: Q3 2027


Project status:


• Land secured for the investment

• Connection conditions obtained

• Signed connection agreement

• Environmental decision in progress

• Work is ongoing to secure the cable route

• Project at pre-RTB stage



Detailed technical documentation and project information are available upon signing an NDA.

Should you notice any Illegal Content on the Platform, or content that violates the law, good practices, or the Terms and Conditions for the provision of services on the greensearch.pl online platform, please contact us directly at: kontakt@greensearch.pl. Please title the message "Report of Illegal Content on the Platform" and include a description of the violation along with a link to the offer containing the relevant content.

Listings added by greensearch - BESS:

No other listings
PARP Logo