Project types
BESS Power
50 MW
Storage Capacity
228 MWh
Project status
Zoning plan amended
Country
Poland
Voivodeship
zachodniopomorskie
County
Kołobrzeski
Grid connection conditions
YES
Operator
Energa
Voltage
110 kV
Line length
2.9 km
Date BP
30/09/2027
Date of COD
31/01/2029
The project includes a large-scale energy storage system with a capacity of 50 MW and a storage capacity of 228 MWh.
Key project parameters:
• Energy storage power: 50 MW
• Energy storage capacity: 228 MWh
• Storage duration: over 4 hours
• Charging capacity: 50 MW
• Discharging capacity: 50 MW
• Connection voltage: 110 kV
• Grid operator: ENERGA-OPERATOR S.A.
• Estimated connection length: approx. 2.9 km
• Estimated connection cost: 1,250,000 PLN
• Planned connection date: 31.01.2029
• Planned RTB status: Q3 2027
Project status:
• Land secured for the investment
• Connection conditions obtained
• Signed connection agreement
• Environmental decision in progress
• Work is ongoing to secure the cable route
• Project at pre-RTB stage
Detailed technical documentation and project information are available upon signing an NDA.
Should you notice any Illegal Content on the Platform, or content that violates the law, good practices, or the Terms and Conditions for the provision of services on the greensearch.pl online platform, please contact us directly at: kontakt@greensearch.pl. Please title the message "Report of Illegal Content on the Platform" and include a description of the violation along with a link to the offer containing the relevant content.