Project types
PV Capacity
192 MWp
Storage Capacity
141 MW
Storage Capacity
600 MWh
Number of turbines
7 units
Project status
Secured land
Country
Poland
Voivodeship
warmińsko-mazurskie
Grid connection conditions
NO
Hybrid project for sale:
Wind farm
Wind power capacity: 64.8 MW
Land reserved for 3 turbines
An additional 6 locations are currently under discussion.
Site located outside a protected area.
Several existing Main Supply Points (GPZ) are located within reasonable proximity.
PV + BESS:
PV capacity: 141 MW
BESS capacity: 141 MW
Land secured – approx. 210 ha.
Project status:
+ Secured lease
- Environmental decision obtained (expected Q4 2027)
- Local Spatial Development Plan (expected Q4 2026)
- Grid connection conditions: in preparation (application submission planned Q2 2027)
- Building Permit: planned Q4 2028
Details, documentation, and locations are available upon contact via greensearch.
Should you notice any Illegal Content on the Platform, or content that violates the law, good practices, or the Terms and Conditions for the provision of services on the greensearch.pl online platform, please contact us directly at: kontakt@greensearch.pl. Please title the message "Report of Illegal Content on the Platform" and include a description of the violation along with a link to the offer containing the relevant content.