Back
greensearch - BESS logo

BESS - 50 MW pre-RTB, COD 2028 (warmińsko-mazurskie)

greensearch - BESS

Project types

Energy storage

BESS Power

50 MW

Storage Capacity

227 MWh

Project status

Zoning plan amended

Country

Poland

Voivodeship

warmińsko-mazurskie

Grid connection conditions

YES

Operator

Energa

Voltage

110 kV

Line length

0.15 km

Date BP

30/09/2027

Date of COD

31/12/2028

Project description

For sale: a large-scale energy storage project (BESS) rated at 50 MW with a capacity of 227 MWh, located in the Warmińsko-

Mazurskie Voivodeship.


Key project parameters:

  • Energy storage power: 50 MW
  • Energy storage capacity: 227 MWh
  • Storage operation duration: over 4 hours
  • Charging power: 50 MW
  • Discharging power: 50 MW
  • Connection voltage: 110 kV
  • Grid operator: Energa-Operator S.A.
  • Estimated connection length: approx. 150 m
  • Estimated connection cost: 1,250,000 PLN
  • Planned connection date as per the connection agreement: 31.12.2028
  • Planned RTB status: Q3 2027


Project status:

  • Land secured for the investment
  • Connection conditions obtained
  • Work is underway on the cable route
  • Building permit in progress
  • Connection agreement - under preparation


Detailed project documentation available upon signing an NDA.

Should you notice any Illegal Content on the Platform, or content that violates the law, good practices, or the Terms and Conditions for the provision of services on the greensearch.pl online platform, please contact us directly at: kontakt@greensearch.pl. Please title the message "Report of Illegal Content on the Platform" and include a description of the violation along with a link to the offer containing the relevant content.

Listings added by greensearch - BESS:

No other listings
PARP Logo