BESS power
24 MW
Storage capacity
75.68 MWh
Project status
Environmental decision received
Country
Poland
Voivodeship
śląskie
Connection conditions
YES
Operator
Tauron
Voltage
15 kV
Line length
3.1 miles
Minimum rent
PLN 60,000/ha
Date BP
December 31, 2026
Date of COD
October 24, 2029
Energy sales
other
Sale of the project
Other
Three energy storage projects located in the Silesian Province (TAURON) are for sale, currently at the pre-RTB stage.
Two projects with parameters:
Charging power: 8 x 1 MW
Discharging power: 8 x 1 MW
Connection power: 8,000 x 1 kW
Storage capacity: 20.64 MWh
(8 × 1 MW / 2.58 MWh)
One project with parameters:
Charging power: 8 MW
Discharging power: 8 MW
Connection power: 8,000 kW
Storage capacity: 34.4 MWh
--
Land secured by a lease agreement.
Length of connection to the GPZ: approx. 3100 m.
Connection agreement signed.
Planned energization: January 24, 2029.
Details, documentation, and plot number available upon contact via greensearch.
If you notice any Illegal Content on the Platform, or content that is contrary to the law, good manners, or the Terms of Service of the Greensearch.pl internet platform, please contact us directly at:greensearch. Please title your message "Reporting illegal content on the Platform" and include a description of the violation along with a link to the offer containing the content in question.