Return
greensearch  BESS logo

240 BESS MW OSDn - PSE - 400kV - Pomorskie

greensearch BESS

Project types

Energy storage

Power

240 MW(p)

Storage capacity

0 MWh

Project status

Secured land

Country

Poland

Voivodeship

pomorskie

Connection conditions

YES

Operator

PSE

Voltage

400 kV

Line length

0 km

Minimum rent

0 PLN/ha

Date BP

October 1, 2030

Date of COD

October 1, 2030

Energy sales

other

Sale of the project

Other

Price

€20,000/MW

Ad description

Distribution system connection project (OSDn) – BESS 240 MW / 240 MW


Connection voltage: 400 kV
Energy storage capacity: 240 MW (feed-in) / 240 MW (draw-off)
Planned date of readiness to supply voltage: October 2030
Estimated connection fee: PLN 14,028,000.00 net + VAT


The project involves connecting a private distribution system, including a 240 MW / 240 MW energy storage facility, to the transmission grid. Connection point: Żarnowiec.


Based on the connection terms issued by the Transmission System Operator (PSE S.A.), the project has been approved for implementation at the 400 kV voltage level, with the target date for energization set for October 2030, assuming that the connection agreement will be signed in 2026.


The estimated connection fee, corresponding to the projected capital expenditures, amounts to PLN 14.03 million net, subject to adjustment during the implementation phase or upon signing the contract.

If you notice any Illegal Content on the Platform, or content that is contrary to the law, good manners, or the Terms of Service of the Greensearch.pl internet platform, please contact us directly at:greensearch. Please title your message "Reporting illegal content on the Platform" and include a description of the violation along with a link to the offer containing the content in question.

Listings posted by greensearch BESS:

No other announcements
PARP logo