Project types
Power
240 MW(p)
Storage capacity
0 MWh
Project status
Secured land
Country
Poland
Voivodeship
pomorskie
Connection conditions
YES
Operator
PSE
Voltage
400 kV
Line length
0 km
Minimum rent
0 PLN/ha
Date BP
October 1, 2030
Date of COD
October 1, 2030
Energy sales
other
Sale of the project
Other
Price
€20,000/MW
Connection voltage: 400 kV
Energy storage capacity: 240 MW (feed-in) / 240 MW (draw-off)
Planned date of readiness to supply voltage: October 2030
Estimated connection fee: PLN 14,028,000.00 net + VAT
The project involves connecting a private distribution system, including a 240 MW / 240 MW energy storage facility, to the transmission grid. Connection point: Żarnowiec.
Based on the connection terms issued by the Transmission System Operator (PSE S.A.), the project has been approved for implementation at the 400 kV voltage level, with the target date for energization set for October 2030, assuming that the connection agreement will be signed in 2026.
The estimated connection fee, corresponding to the projected capital expenditures, amounts to PLN 14.03 million net, subject to adjustment during the implementation phase or upon signing the contract.
If you notice any Illegal Content on the Platform, or content that is contrary to the law, good manners, or the Terms of Service of the Greensearch.pl internet platform, please contact us directly at:greensearch. Please title your message "Reporting illegal content on the Platform" and include a description of the violation along with a link to the offer containing the content in question.