Project types
Power
240 MW(p)
Project status
Secured land
Country
Poland
Voivodeship
zachodniopomorskie
Connection conditions
YES
Operator
PSE
Voltage
400 kV
Line length
0 km
Minimum rent
0 PLN/ha
Date BP
June 6, 2030
Date of COD
June 1, 2031
Energy sales
other
Sale of the project
Other
Price
€20,000/MW
Distribution system connection project (OSDn) – BESS 240 MW / 240 MW
Connection voltage: 400 kV
Energy storage capacity: 240 MW (feed-in) / 240 MW (feed-out)
Planned date of readiness for voltage supply: June 2031.
Estimated connection fee: PLN 25,565,500.00 net + VAT
The project involves connecting a distribution system integrated with energy storage facilities with a total installed capacity of 240 MW (charging and discharging) to the transmission grid.
In accordance with the connection conditions issued by Polskie Sieci Elektroenergetyczne S.A. (PSE S.A.), the investment is planned to be implemented at a voltage level of 400 kV, with the connection point at the 400/110 kV Żydowo Kierzkowo station (rail bridge in the 400 kV switchyard).
The earliest date for ensuring readiness to supply voltage has been set for June 2031, assuming that the connection agreement is concluded in May 2026. This date may change during the negotiation of the connection agreement and depending on the Operator's network investment schedule.
The estimated connection fee, determined on the basis of the connection conditions, is PLN 25,565,500.00 net + VAT, with the possibility of updating at the stage of concluding the connection agreement.
If you notice any Illegal Content on the Platform, or content that is contrary to the law, good manners, or the Terms of Service of the Greensearch.pl internet platform, please contact us directly at:greensearch. Please title your message "Reporting illegal content on the Platform" and include a description of the violation along with a link to the offer containing the content in question.