Project types
BESS power
16 MW
Storage capacity
68.6 MWh
Project status
Environmental decision received
Country
Poland
Voivodeship
śląskie
Connection conditions
YES
Operator
Tauron
Voltage
15 kV
Line length
2 km
Minimum rent
PLN 15,000/ha
Date BP
December 31, 2026
Date of COD
March 12, 2029
Energy sales
other
Sale of the project
Other
Two identical energy storage projects located in the Silesian Province (TAURON) are for sale, at the pre-RTB stage.
Charging power: 8 MW
Discharge power: 8 MW
Connection power: 8,000 kW
Storage capacity: 34.4 MWh
Land secured by a lease agreement.
Length of connection to the GPZ: approx. 2000 m.
Connection agreement signed.
Planned energization: March 12, 2029.
Connection cost according to UP: 2 x PLN 15,375 gross.
Details, documentation, and plot number available upon contact via greensearch.
If you notice any Illegal Content on the Platform, or content that is contrary to the law, good manners, or the Terms of Service of the Greensearch.pl internet platform, please contact us directly at:greensearch. Please title your message "Reporting illegal content on the Platform" and include a description of the violation along with a link to the offer containing the content in question.